From a 500-row sample across 10 columns.
managing_agencyreporting_periodmanaging_agencyreporting_periodpidcurrent_phase+2| reporting_period | managing_agency | pid | agency_project_name | current_phase | completion_date | completion_date_type | data_date | variance_day |
|---|---|---|---|---|---|---|---|---|
| 202305 | CUNY | 72 | BKLYNC-Performing Arts Center | Close-out | 2018-07-03T00:00:00.000 | Actual | 2023-04-26T00:00:00.000 | — |
| 202305 | CUNY | 73 | BARUCH-17 Lexington Avenue | Close-out | 2016-06-01T00:00:00.000 |
The machine field names SoQL needs, with the publisher's own description of each.
| Field | Type | Description | Null | Values |
|---|---|---|---|---|
reporting_period | categorical | The year and the month the report is published (format YYYYMM). The dataset is updated 3 times a year following OMB’s commitment plan release date in Jan/May/Sep. | 0% | 202401202509202409of 10 |
managing_agency | categorical | Common acronym of the city agency that is responsible for managing the construction and delivery of the capital project. This value is derived from the three digit managing agency code. | 0% | DPRDDCDEPof 13 |
pid | integer | Unique identifier that represent a set of schedule managed by agency. | 0% | 400943584233 |
agency_project_name | text | The name of the project in the managing agency's project management system |
GET /api/datasets/95tx-snak GET /api/datasets/95tx-snak/quality GET /api/datasets/95tx-snak/related GET /api/columns?dataset=95tx-snak
| Actual |
| 2023-04-26T00:00:00.000 |
| — |
| 202305 | CUNY | 74 | HTSCC-ADA Work | Close-out | 2010-12-20T00:00:00.000 | Actual | 2023-04-26T00:00:00.000 | — |
| 202305 | CUNY | 75 | HTSCC-HVAC Work | Pre-Design | — | Forecast | 2023-04-26T00:00:00.000 | — |
| 202309 | CUNY | 75 | HTSCC-HVAC Work | Pre-Design | — | Forecast | 2024-02-02T00:00:00.000 | — |
| 202401 | CUNY | 75 | HTSCC-HVAC Work | Design | 2025-05-12T00:00:00.000 | Forecast | 2024-05-03T00:00:00.000 | — |
| 202405 | CUNY | 75 | HTSCC-HVAC Work | Design | 2025-05-12T00:00:00.000 | Forecast | 2024-05-03T00:00:00.000 | 0 |
| 202409 | CUNY | 75 | HTSCC-HVAC Work | Construction | 2025-05-12T00:00:00.000 | Forecast | 2024-11-15T00:00:00.000 | 0 |
| 202501 | CUNY | 75 | HTSCC-HVAC Work | Construction | 2025-05-12T00:00:00.000 | Forecast | 2025-03-20T00:00:00.000 | 0 |
| 202505 | CUNY | 75 | HTSCC-HVAC Work | Close-out | 2024-06-06T00:00:00.000 | Actual | 2025-06-25T00:00:00.000 | -340 |
| 0% |
FUEL TANK REPLACEMENTReconstruction of Existi…HWPR24 Series Standard P… |
current_phase | categorical | The phase the project is in: Pre-Design, Design, Construction Procurement, Construction, or Close-out | 1% | DesignConstructionPre-Designof 10 |
completion_date | datetime | The date when the entire project is expected to be completed or has completed (driven by 'completion date type' field.) | 24% | 2026-06-30T00:00:00.0002025-06-30T00:00:00.0002026-09-30T00:00:00.000 |
completion_date_type | categorical | This field specify if the 'completion date' is a forecast date or an actual date | 0% | ForecastActualof 2 |
variance_day | integer | This is the difference calculated by 'completion date' of current row value subtracted by the same column of prior nearest reporting period. | 37% | 0365-1 |
reason_for_forecast_completion_change | categorical | This is the rationale provided when the forecasted completion date differs from the previously forecasted date. | 89% | PROJECT DELAYED DUE TO C…PROJECT DELAYED PENDING …PROJECT DELAYED DUE TO B…of 13 |
data_date | datetime | The actual date this record submitted by agency | 0% | 2024-11-01T00:00:00.0002024-04-22T00:00:00.0002024-02-16T00:00:00.000 |